The replacement of five circuit breakers of an outdoor 150 kV switchgear has been completed at the Apatitskaya CHPP of TGC-1 PJSC. Outdated oil circuit breakers were replaced with modern SF6 equipment.
TGC-1 engineers have completed the overhaul of hydroelectric unit No. 1 at the Yushkozerskaya HPP to enhance reliability of the electricity supply for residents of the Kaleval and Muyezersky districts.
TGC-1 releases abbreviated consolidated Financial Statements for the 6 months period, ended 30 June 2021 prepared in accordance with International Financial Reporting Standards (IFRS).
Power unit No. 4 of the Yuzhnaya CHPP of TGC-1 PJSC has passed a competitive selection and since July 2021 participates in ensuring the system reliability of the Unified Power System of Russia in terms of rated primary frequency control (RPFC)