TGC-1 presents its performance highlights for H1 2020

28 July 2020

Electricity output of TGC-1, including JSC Murmanskaya CHPP, for 6 month 2020 comprised 15,037.6 million kWh, which is 0.3% lower than for the same period of 2019.

Comparable electricity output at TGC-1 condensed heat power plants decreased by 11.7%. The electricity output by hydro power plants increased by 17.8% due to the higher water content in the regions where company operates in the reporting period.

TGC-1 electricity output summary (million kWh)

 

6M 2019

6M 2020

Difference

Nevsky branch

9,835.2

9,242.9

-6.0%

Karelsky branch

1,948.4

2,151.4

+10.4%

Kolsky branch

3,284.3

3,633.7

+10.6%

TGC-1 total

15,067.9

15,028.0

-0.3%

JSC Murmanskaya CHPP

9.9

9.6

-3.0%

TGC-1 total, including
JSC Murmanskaya CHPP

15,077.8

15,037.6

-0.3%

The volume of heat output from collectors of TGC-1, including JSC Murmanskaya CHPP, comprised 13,335.4 thousand Gcal, which is 2.9% lower than for the H1 2019 due to the higher ambient temperatures in the reporting period.

TGC-1 heat output summary (thousand Gcal)

 

6M 2019

6M 2020

Difference

Nevsky branch

10,688.7

10,442.8

-2.3%

Karelsky branch

967.3

920.8

-4.8%

Kolsky branch

843.2

795.2

-5.7%

TGC-1 total

12,499.2

12,158.8

-2.7%

JSC Murmanskaya CHPP

1,235.6

1,176.6

-4.8%

TGC-1 total, including
JSC Murmanskaya CHPP

13,734.8

13,335.4

-2.9%

For more information about the results of the company’s production performance, please visit the Reports section of the corporate website.

About

TGC-1 (part of Gazprom Energoholding Group) is a leading producer and supplier of electricity and heat in the North-West of Russia. TGC-1 comprises 52 power plants within four constituent entities of the Russian Federation: St. Petersburg, the Republic of Karelia, and Leningrad and Murmansk Oblasts.

TGC-1's installed electric capacity is 6.9 GW, and heat capacity is 13.5 thousand Gcal/h. Major Shareholders: Gazprom Energoholding LLC (51.79%) and Fortum Power and Heat Oy (29.45%).