JSC TGC-1: 2011 IFRS Results
JSC TGC-1 releases audited consolidated financial statements (prepared in accordance with IFRS) for the year ended 31 December 2011.
-
25.04.2012
TGC-1 will release 12M 2011 IFRS consolidated financial results on Thursday, 26th April
TGC-1 will release 12M 2011 IFRS consolidated financial results on Thursday, 26th April, on the company’s website www.tgc1.ru, followed by a Conference Call in Russian and English.
-
12.03.2012
Approval of candidates to the TGC-1’s Board of Directors
The TGC-1’s Board of Directors approved a list of candidates to the Company’s Board of Directors to be voted for at the Annual General Shareholder Meeting.
-
12.03.2012
TGC-1 issues bonds of series 04
On March 11, 2012, TGC-1 has successfully completed issuing 10-year bonds of series 04 at MICEX. The bonds were completely sold out in the market.
-
05.03.2012
TGC-1’s net profit under RAS increased by 4% in 2011
JSC TGC-1 published its financial statements for 2011, made under Russian Accounting Standards (RAS).
-
05.03.2012
TGC-1 sets an interest rate for the 11-14th coupons of the bonds of series 01
On March 2, 2012, TGC-1 set an interest rate equal to 7.6% per annum for 11-14th coupons of TGC-1’s bonds of series 01. The interests to be paid are 37 rubles 90 kopecks per each Issuer’s bond.
-
02.03.2012
TGC-1 was nominated as the best pass-holder of Vodokanal Company in 2011
March 1, 2012 in Museum complex "The Universe of Water" (St.Petersburg, 56 Shpalernaya Str.) there were called nominees of the Cristal Drop Vodokanal Prize in 2011.
-
20.02.2012
Lapland Centre for Economic Development, Transport and the Environment will be new regulator of Lake Inari
Since February 20, 2012 Lapland Centre for Economic Development, Transport and the Environment will be new regulator of Lake Inari, which is in use of three states — Russian Federation, Norway and Finland.
-
20.02.2012
TGC-1 has set a new nomination at the International Winter Fest 'Hyperboreya' in Karelia
On February 18, 2012 the International Winter Fest 'Hyperboreya' in Karelia called its nominees.
-
16.02.2012
Sergey Kozyrev, vice-governor of St.Petersburg, visited Pravoberezhnaya CHP TGC-1
On February 16, 2012 Sergey Kozyrev, vice-governor of St.Petersburg, visited Pravoberezhnaya CHP TGC-1 — a new-built plant with total capacity of 1,120 GCal/h.
-
14.02.2012
TGC-1’s Board of Directors Approved Expansion of Two Projects of the Company’s Investment Programme
TGC-1’s Board of Directors considered a range of corporate matters and approved revision of the Pervomayskaya and Central CHPPs renovation projects.
-
07.02.2012
TGC-1 finished the refurbishment of the hydraulic unit at the Belomorskaya HPP
New 3d hydraulic unit was renovated at the Belomorskaya HPP in accordance with the renovation programme of TGC-1.
-
25.01.2012
TGC-1 has set new equipment at Putkinskaya HPP in Karelia
TGC-1 has finished the large project of refurbishment three units' speed control at Putkinskaya HPP (Kem' HPPs Cascade) in Karelia.
-
13.01.2012
Finnish energy engineers and managers visited TGC-1 plant
Industrial Energy Fund members (Finland) visited TGC-1 Yuzhnaya CHP plant on January 12, 2012.
-
28.12.2011
JSC TGC-1 placed bonds for financing of its Investment programm
JSC TGC-1 placed bonds for financing of its Investment programm. The bonded loan of JSC TGC-1 series 03 was placed by open subscription on December 27, 2011. The bonded loan was fully bought out by the market.
-
26.12.2011
Interest rate is defined for the first coupon of bonds of JSC TGC-1 series 03
On December 27, 2011 placement of 2 million bonds of JSC TGC-1 of series 03 with a nominal value of 1 thousand rubles each for the period of 10 years by open subscription will start at MICEX stock exchange.
-
21.12.2011
Cristmas Fair opens in St. Petersburg
December 21, 2011 in the very centre of the city there opens Christmas Charity Fair. TGC-1 is the major sponsor of the fair, which will be on till the end of holidays — January 14, 2011.
-
12.12.2011
Bonds of JSC TGC-1 series 03-06 are registered by FFMS of Russia
On December 8, 2011 Federal Financial Markets Service of Russia registered the issues and prospectus of bonds of JSC TGC-1 series three to six for the total amount of 8 billion rubles
-
06.12.2011
JSC TGC-1: 9M 2011 IFRS Results
JSC TGC-1 releases its interim abbreviated consolidated Financial Statements for the 9 months period ended September 30, 2011 prepared in accordance with International Financial Reporting Standards (IFRS).
-
06.12.2011
Oldest Russian Hydro Power Plant refurbishment finish
Hamekoski HPP (Suna HPPs Cascade of Karelia), set in 1903, is ready to work with new capacities.