Environmental Measures

Planned environmental protection measures for 2021

  • Development of projects for the construction of noise screens in the direction of Veterinarniy lane at the Petrozavodskaya CHPP (to be started in 2021, carryover)
  • Reconstruction of the water disposal system at Petrozavodskaya CHPP including construction of treatment plants (carryover)
  • Measures to ensure environmental safety during storage of fuel oil and its draining from railway tanks at Avtovskaya CHPP (carryover from previous periods)
  • Development of project for reconstruction of sewage networks with the separation of flows and the construction of treatment plants at the discharge into the reservoir and public sewer at Avtovskaya CHPP (carryover) 
  • Reconstruction of sewage networks with the construction of the sewage treatment plants of Vasileostrovskaya CHPP (carryover)
  • Development of the modernization project for local treatment plants of Pervomayskaya CHPP at the discharge to public sewer (carryover)
  • Reconstruction of sewage networks, installation of dewatering of liquid technical waste sludge, construction of local treatment plants of Pravoberezhnaya CHPP at the discharge to public sewer (commissioning works were fulfilled last year, project completion)
  • Development of modernization project for the treatment plants complex of Severnaya CHPP (carryover)
  • Modernization of local treatment plants of Yuzhnaya CHPP (carryover)
  • Reconstruction of the sewage system with the installation of commercial metering stations and the construction of PP-2 treatment plants at Centralnaya CHPP (carryover)
  • Modernization of the sewage system with the installation of commercial metering stations and the construction of PP-1 treatment plants at Centralnaya CHPP (carryover)